Meadows Way overnight road closures announced for bus lane improvement works

Two phases of overnight road closures are planned on Meadows Way in Nottingham later this month as work continues on improvements to bus services along the route.

Nottingham City Council has confirmed that resurfacing and road repairs will take place between Monday 23 November and Friday 4 December 2026, with sections of Meadows Way closed overnight between 8pm and 6am.

meadows way 2.png

The work forms part of the Greater Nottingham Bus Service Improvement Plan, supported by funding from the Department for Transport.

Dates and locations of overnight closures

The resurfacing programme will be carried out in two phases:

  • Phase 1 – Arkwright Walk to Kirkwhite Walk: Monday 23 November to Friday 27 November, between 8pm and 6am each night.

  • Phase 2 – Kirkwhite Walk to Bathley Street: Monday 30 November to Friday 4 December, between 8pm and 6am each night.

Temporary road closures will apply to the section of Meadows Way being worked on during each phase.

Motorists will not be permitted to park along Meadows Way during the overnight resurfacing works, between 8pm and 6am.

Signed diversion routes will be provided throughout the closures.

Wider improvements to Meadows Way

The scheme is intended to reduce delays for buses travelling towards Nottingham city centre along Meadows Way, which is a busy bus route.

Improvements being introduced as part of the project include:

  • New bus lanes to improve journey times and reliability.

  • Relocation of existing bus stops.

  • Replacement of the current zebra crossing with a new push-button pedestrian crossing.

  • Extensions to off-street parking areas.

  • Removal of on-road parking along Meadows Way.

  • A new right-turn lane into Mabel Street.

  • Improvements to pavements and pedestrian facilities.

  • Upgrades to cycling facilities.

The council says the wider scheme is designed to improve bus punctuality, encourage greater use of public transport and reduce congestion.

The improvements are also intended to support access to employment, local businesses and new housing developments.

The overnight resurfacing programme is scheduled to conclude on Friday 4 December, subject to the works progressing as planned.