Roadworks on Maid Marian Way in Nottingham will finish on Thursday 19 November, with permanent traffic lights due to replace the temporary signals at the Canal Street junction from early morning.
Transport Nottingham said the change would restore the road to the layout in place before the demolition of the former NCP car park at Broad Marsh.
The contraflow was lifted overnight on 11–12 November, around two weeks ahead of schedule. Lanes in both directions and the bus lane reopened, along with Greyfriar Gate. Temporary lights stayed in place at the Canal Street junction while contractors finished work on the road.
The contraflow had been in place since 28 September. Traffic was reduced to one lane in each direction on the northbound carriageway while contractors demolished the section of the car park that extended over Maid Marian Way. Bus operators reported delays of up to 90 minutes on the first day, with some services diverted or cut short.
The car park demolition was part of the wider Broad Marsh redevelopment, which also includes work at the former Nottingham College site. Homes England thanked road users for their patience and said it would provide further updates as the project progresses.