A52 Nottingham Knight junction improvements delayed by one year

National Highways have updated on the A52 junctions work.

National Highways said on 16 August:

‘When we initially designed the A52 Nottingham Junctions (larger) scheme, our traffic modelling was based on proposed local road developments in the area.

‘However, uncertainty around timelines led us to exclude these developments from our planning. As a result, we needed to carry out additional traffic modelling to fully assess the benefits and impacts of our planned improvements.

‘During this time, we also continued to progress our design and engage with key stakeholders.

- Advertisement -

‘Because of this additional work, we now expect to begin construction in autumn 2025 and not in autumn 2024 as planned.

‘We appreciate your understanding, especially those keen to see these improvements move forward. However, ensuring we deliver the best scheme possible remains our top priority.

•  Traffic disruption as QMC bridge overnight repair works start on Monday and last until Summer 2025

At Nottingham Knight junction:

Screenshot 2024 08 16 at 15.12.16
The scheme design for Nottingham Knight roundabout A52

The roundabout will be enlarged to the east of
the existing roundabout and redesigned as a
through-about junction with a new link road from
the A52 eastbound

All approaches to the junction will be widened to
provide extra lanes and increase capacity at the
junction.

This includes:

increasing the A52 eastbound approach
from 3 lanes to 4

increasing the A52 westbound approach
from 3 lanes to 4

closing the access from Landmere Lane to
A52 eastbound

all crossing points will be designed for users
with disabilities

new signalised junctions and crossings

Follow The Wire on TikTok, Facebook, X, Instagram. Send your story to newsdesk@westbridgfordwire.com or on 0115 772 0418