Planned roadworks in Nottingham this week.
- Monday 1 April 2024 – Thursday 31 July 2025: Road closure on length of Denman Street East, Radford, between Highhurst Street and Thackery Street, for development works
- Monday 27 May – Monday 15 July: Multi-way temporary signals off peak on Woodborough Road at junction of St Jude’s Avenue, Lucknow Drive, Mapperley Hall Drive, Thyra Grove and Denmark Grove for Cadent gas works
- Monday 3 June – Wednesday 7 August: Road Closure of Montpelier Road both directions at the junction of Lace Street between 24 June & 22 July 24, Road Closure of Montpelier Road both directions at the junction of Marlborough Street between 26 June & 12 July, Road Closure of Montpelier Road both directions at the junction of Claude Street between 1 July & 17 July and
Parking suspension both sides of Montpelier Road for its entire length for the duration of the works, for Cadent Gasworks
- Monday 17 June – Monday 15 July 9.30am – 3.30pm: Lane closure outside Bolero Square / Motorpoint Arena for bollard installation
- Monday 10 – Friday 21 June, 9:30am – 3pm: 3-way traffic lights on Windmill Lane, Sneinton for EV charger cable installation
- Monday 17 – Friday 21 June: Road closure on Sandon Road, Berridge, from junction with Nottingham Road to outside No.2 for National Grid works
- Friday 21 June 3am – 6am: 3-way lights on Sneinton Dale for Severn Trent Water works
- Friday 21 June 3am – 6am:Lane closure on Daleside Road for Severn Trent Water works
- Saturday 22 & Sunday 23 June 7am – 4pm: Lane closures on Western Boulevard at junction with Beechdale Road for traffic lights works
- Sunday 23 June 9.30 – 3.30pm: 3-way lights on Wollaton Vale for Severn Trent Water works
- Sunday 23 June 9.30 – 3.30pm: 2-way lights on Alfreton Road for Severn Trent Water works
- Sunday 23 June 9.30 – 3.30pm: 2-way lights on Abbey Bridge for Severn Trent Water works
- Sunday 23 – Thursday 27 June, 10pm – 6am: Road closure on London Road inbound between Station Street & Canal Street for crane operation
- Sunday 23 – Sunday 30 June: 2-way lights with stop / go boards on Ventura Drive, adjacent to junction with Hucknall Lane for new utilities connections
- Tuesday 25 June 9.30am – 3.30pm: Lane closure on Mansfield Road between Burnham Street & Haydn Road for display board maintenance works
- Friday 28 June 11.30pm – Saturday 29 June 5.30am: 3-way traffic signals at Arkwright Street junction with Meadows Way for tramway works
- Monday 1 – Monday 15 July: Road closure between Talbot Street/Burton Street and Upper Parliament Street during tramworks
- Monday 1 July – Saturday 20 July: Road closure between 324 & 344 Trowell Roadfor resurfacing works
- Until 29 August 2024: Road closure on Howard Street, St Ann’s for construction works
- Until 31 March 2025: Parking bay suspension and partial road closure on Kent Street, St Ann’s for construction works
- Until Thursday 31 July 2025: Road closure of Thackeray Street and Parking bay suspension on Denman Street East, Highurst Street & Boden Street for new development