Nottinghamshire County Council will repair damaged roads across these locations over the next month.
With works across various parts of the road network already under way, here is a list of larger-scaled works the authority’s highway team, VIA, is aiming to start between Tuesday, May 26 and Monday, June 22:
Ashfield
- A611 Derby Road, Kirkby in Ashfield, resurfacing works estimated to start May 26 and finish June 5 – Shoulder of Mutton Hill to surface change approaching B6020 Diamond Avenue junction.
- A611 Derby Road / B6139 Coxmoor Road junction, Sutton in Ashfield, resurfacing works to the full junction estimated to start May 26 and finish June 5.
- C216 Beardall Street, Hucknall, resurfacing works from B6009 Watnall Road to Portland Road, estimated to start on June 8 and finish on June 19.
- C150 High Pavement, Sutton in Ashfield (across Ashfields / Sutton Central and East), resurfacing works from Prospect Place to, and including, Spring Road roundabout, estimated to start on June 22 and finish on June 26.
Bassetlaw
- B1403 Clayworth Common / Hayton Road, Hayton, surface dressing preparation patching works from Town Street / Wheatley Road, Clayworth to junction B1403 Main Street The Boat Inn / Burntley’s Road, Hayton – estimated to start on June 8 and finish on June 19.
Broxtowe
- Peveril Road, Beeston, resurfacing workings estimated to start May 26 and finish May 29 – From Abbey Road junction to o/s No 86.
- Noel Street, Kimberley, resurfacing works to the whole length of road estimated to start on May 26 and finish May 29.
- Ryecroft Street, Stapleford, resurfacing works estimated to start from May 26 and finish May 31 – from o/s No75 to o/s No87 approx 30m north of Welch Avenue – concrete section.
- Plumptre Way, Eastwood, resurfacing works from Nottingham Road to The Island (both lanes), estimated to start on June 22 and finish on July 3.
Gedling
- Lambley Avenue, Mapperley, resurfacing works to the whole length of road, estimated to start on May 26 and finish on May 31.
- Shelford Road, Gedling (Phase 1), resurfacing from Arnold Lane to Freda Avenue, estimated to start on June 1 and finish on June 12.
- Longue Drive, Calverton, resurfacing works from Georges Lane to Jumelles Drive and from Rowan Close to Jumelles Drive, estimated to start on June 1 and finish on June 5.
- Prospect Road, Carlton, resurfacing from Valley Road to Standhill Road, estimated to start on June 1 and finish on June 12.
Mansfield
- Cox’s Lane, Mansfield Woodhouse, resurfacing works to the whole length of road including Sunnydale roundabout, estimated to start on May 26 and finish on June 5.
- Slant Lane, Mansfield Woodhouse, resurfacing works from Brown Avenue to Shakespeare Avenue, estimated to start on May 26 and finish on June 5.
- A617 Rainworth Bypass (Westbound carriageway, across Mansfield East / Blidworth), resurfacing works from Rufford Colliery Lane junction to A6191 roundabout (Westbound), estimated to start on June 8 and finish on July 3.
- A6191 Chesterfield Road South, Mansfield (across Mansfield West / Mansfield North), surface dressing preparation patching works from A617 Pleasley Hill Way junction to A6009 Rosemary Street junction, estimated to start on June 8 and finish on July 3.
- A6191 Ratcliffe Gate, Mansfield, resurfacing works from St. Peters Way to surface change at Frederick Street (including St. Peters Way junction), estimated to start on June 22 and finish on July 3.
Newark and Sherwood
- C3 Grange Lane, Balderton – continuation of resurfacing work from 2025/26 financial year, estimated to start on June 15 and finish on July 3.
- C83 Main Street, Balderton (across Balderton / Newark East), resurfacing works from surface change at Bridge Court to Church Lane, estimated to start on June 22 and finish on July 3.
Rushcliffe
- Morkinshire Crescent, Cotgrave, resurfacing works to the whole length of road, estimated to start on June 1 and finish on June 5.
- Stonebridge Drive, East Leake, resurfacing from Gotham Road to o/s no 4 approx 15m past Carlton Crescent, estimated to start on June 1 and finish on June 5.
- C26 Costock Road / Leake Road, East Leake (across Ruddington / Keyworth), resurfacing works from Meeting House Close to approx 100m past Brook Furlong Farm entrance, estimated to start on June 8 and finish on June 19.
- Works Lane, Barnstone, resurfacing works to the adopted section, estimated to start on June 15 and finish on June 19.