Updates: Waterside Bridge progress as installation works continue

Transport Nottingham provided this update as work continues on the new Waterside Bridge in West Bridgford and Nottingham as part of the Transforming Cities project.

Transport Nottingham said in an update on Wednesday 3 September:

‘The bridge is now being assembled at Trent Basin, the deck sections of the bridge that arrived in the week commencing 18 August have now been lifted into place along side the basin and during the first week of September, the arch sections are arriving on site for installation.

542018386 1371900774936766 8483696648431965891 n
© Transport Nottingham
Works have begun to prepare the surface that the huge crane will sit on when it lifts the bridge into place.’
541296382 1371900734936770 6222006166486100472 n
© Transport Nottingham

Other recent progress includes:

  • Ongoing piling works to create the foundations for the bridge structure and ramps.

    - Advertisement -
  • Installation of a temporary sheet pile along the riverbank to secure the edge during construction.

  • Construction of a platform to support the crane that will lift the bridge into place this November.

Meanwhile, over in Hucknall at Briton’s, the bridge structure has been transported in sections under police escort to a specialist facility for painting. Once complete, it will return to Nottingham later this month, ready to be reassembled at the riverside in preparation for installation this autumn.

Photo 13

Curious about how the bridge will be built and lifted into place? Check out the animation for a step-by-step look at the construction process, the lifting operation, and a preview of the completed bridge.